Liability of the carrier

Delay in delivery shall be said to occur when the goods have not been delivered within the agreed time-limit or when, failing an agreed time-limit, the actual duration of the carriage having regard to the circumstances of the case, and in particular, in the case of partial loads, the time required for making up a complete load in the normal way, exceeds the time it would be reasonable to allow a diligent carrier.