WASTE PREVENTION AUDIT Protocol van 1996 bij het Verdrag inzake de voorkoming van verontreiniging van de zee ten gevolge van het storten van afval en andere stoffen van 1972

2. The initial stages in assessing alternatives to dumping should, as appropriate, include an evaluation of:

.1 types, amounts and relative hazard of wastes generated;

.2 details of the production process and the sources of wastes within that process; and

.3 feasibility of the following waste reduction/prevention techniques:

.1 product reformulation;

.2 clean production technologies;

.3 process modification;

.4 input substitution; and

.5 on-site, closed-loop recycling.

3. In general terms, if the required audit reveals that opportunities exist for waste prevention at source, an applicant is expected to formulate and implement a waste prevention strategy, in collaboration with relevant local and national agencies, which includes specific waste reduction targets and provision for further waste prevention audits to ensure that these targets are being met. Permit issuance or renewal decisions shall assure compliance with any resulting waste reduction and prevention requirements.

4. For dredged material, the goal of waste management should be to identify and control the sources of contamination. This should be achieved through implementation of waste prevention strategies and requires collaboration between the relevant local and national agencies involved with the control of point and non-point sources of pollution. Until this objective is met, the problems of contaminated dredged material may be addressed by using disposal management techniques at sea or on land.

Regeling
Protocol van 1996 bij het Verdrag inzake de voorkoming van verontreiniging van de zee ten gevolge van het storten van afval en andere stoffen van 1972