10.3 — Runway pavement overlays Besluit toezicht luchtvaart BES

Runway pavement overlays

Note – The following specifications are intended for runway pavement overlay projects when the runway is to be returned to an operational status before overlay of the entire runway is complete thus normally necessitating a temporary ramp between the new and old runway surfaces. Guidance on overlaying pavements and assessing their operational status is given in the Aerodrome Design Manual, Part 3.

10.3.1 The longitudinal slope of the temporary ramp, measured with reference to the existing runway surface or previous overlay course, shall be:

a) 0.5 to 1.0 per cent for overlays up to and including 5 cm in thickness; and

b) not more than 0.5 per cent for overlays more than 5 cm in thickness.

10.3.2 Overlaying shall proceed from one end of the runway toward the other end so that based on runway utilization most aircraft operations will experience a down ramp.

10.3.3 The entire width of the runway shall be overlaid during each work session.

10.3.4 Before a runway being overlaid is returned to a temporary operational status, a runway centre line marking conforming to the specifications in Section 5.2.3 shall be provided. Additionally, the location of any temporary threshold shall be identified by a 3.6 m wide transverse stripe.

Regeling
Besluit toezicht luchtvaart BES
Soort
AMvB-BES
Geldend vanaf
01-01-2021
BWB-id
BWBR0028721
Versie
2021-01-01_0

In de hele regeling · Officiële tekst op wetten.overheid.nl